Hi ESdat community, What is the best procedure to collapse all of the PIDs into a sinlge PID. All of these will be within the one SID. Thanks in advance, James
|
|
|
|
Rank: Administration
Groups: Registered, Administrators Posts: 498 Location: Byron Bay Was thanked: 19 time(s) in 19 post(s)
|
Hi James, THe PID column in the ESdat data tables references a Project ID, hence what your asking is how can you consolidate multiple projects into one project. There is no global way to do it, you would need to edit the PID values in the data tables, or export an EDIF, delete the project and reimport into the correct project. I assume this need is because a single project has been created twice by different users and with a sightly different "Project ID" and the data needs to be consolidated? Warwick
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.